Carrying out work on repairing a dam with a water transfer device. Chapter V calculation of the economic cost of the project Example of an estimate for the repair of an earthen dam

The order is placed by a specialized organization
Mailing address Russian Federation, 142784, Moscow, Moskovsky, microdistrict 1, 19a
Actual address Russian Federation, 142784, Moscow, Urban settlement Moskovsky ter, microdistrict 1, no. 19a
Telephone 7-495-8418147
Fax 7-495-8418147
Email [email protected]
The contact person Tikhonov Alexey Borisovich

Subject of contract

Subject of contract Carrying out repair work on a dam with a water bypass device
Initial (maximum) contract price RUR 497,970.00
Quantity of goods, volume of work or services see documentation
OKDP
Place of delivery of goods, performance of work or provision of services Moscow, Moskovsky settlement, Meshkovo village
Delivery time for goods, performance of work or provision of services within 20 calendar days from the date of conclusion of the contract
Customer Administration of the Moskovsky settlement

Related Documentation

  • . estimate dam Meshkovo_b 600-7, estimate dam Meshkovo_b 600-7.xls
  • . draft contract, draft contract.docx
  • . Auction documentation, AD.docx
  • . Terms of reference for dam repairs, Terms of reference for dam repairs.doc
  • The Ministry of Defense spoke about protecting Moscow from a missile attack

    Moscow's missile defense system complies modern conditions and will not become obsolete in the coming decades, said the commander of the missile defense unit, Major General Sergei Grabchuk.

  • Muscovites handed over more than 22 thousand New Year trees for recycling

    Since January 5, residents of the capital have already handed over for recycling more than 22 thousand New Year trees; last year, during the same time, half as much was collected. Deputy Mayor of Moscow Pyotr Biryukov told reporters about this. According to Biryukov, last year only 12 thousand trees were collected in the first two weeks of the campaign.

Similar lots

    Municipal state-financed organization municipality"Kholmsky city district" "Capital construction department"

    Federal State Budgetary Institution of Culture "State Museum-Reserve "Peterhof"

  • An open competition for the right to conclude a contract to carry out work on the project: “Development and implementation of a comprehensive project for the reconstruction of the Volga-Don shipping canal. Stage II." 2 (second) stage. Start-up complex reconstruction of waterworks No. 7; launch complexes V, III technical re-equipment pumping station No. 32 (units No. 1, 2), a unified automated information and control system ( one system dispatching)

    Federal Budgetary Institution "Administration of the Volga-Don Basin of Inland Waterways"

STATE ESTIMATED STANDARDS

STATE ELEMENTAL ESTIMATED STANDARDS
FOR CONSTRUCTION AND SPECIAL
CONSTRUCTION WORKS

GESN 81-02-36-2001

Part 36

EARTH STRUCTURES
HYDRAULIC STRUCTURES

Moscow 2009

State estimate standards. State elemental estimate standards for construction and special construction works.

GESN 81-02-36-2001 Part 36. Earthen structures of hydraulic structures

State estimate standards State element estimate standards for construction and special construction work (hereinafter referred to as GESN) are intended to determine the need for resources (labor costs of construction workers, machinists, operating time construction machines and mechanisms, material resources) when performing construction and special construction work and for drawing up estimates (estimates) on their basis for the production of these works using resource and resource-index methods.

GESN are the initial standards for the development of other estimate standards: unit prices at the federal, territorial and sectoral levels, individual and consolidated estimate standards.

DEVELOPEDFederal Center for Pricing in Construction and the Building Materials Industry

APPROVED by order of the Ministry of Regional Development Russian Federation dated November 17, 2008 No. 253

STATE ELEMENTAL ESTIMATED STANDARDS
FOR CONSTRUCTION AND SPECIAL CONSTRUCTION WORKS

GESN-36-2001

Part 36. Earthen structures of hydraulic structures

Section 1. EARTH STRUCTURES OF HYDRAULIC STRUCTURES

Subsection 1.1 DAMs, dikes, embankments

Table GESN 36-01-001 Dry construction of dams, dikes, embankments and the bottom of screens and cores

Scope of work:

01. Leveling the soil in layers. 02. Soil compaction with moisture. 03. Loosening the compacted underlying layer of clay soil before laying the subsequent one. 04. Construction and maintenance of entrances, exits and driveways along the embankment. 05. Cleaning of bodies Vehicle when unloading clay soils.

Meter: 1000 m 3 soil

Dry construction of dams, dikes, embankments and the bottom of screens and cores:

36-01-001-01 from non-cohesive soils with rollers weighing up to 16 tons

36-01-001-02 from non-cohesive soils with rollers weighing over 16 tons

36-01-001-03 from cohesive soils with rollers weighing up to 16 tons

36-01-001-04from cohesive soils with rollers weighing over 16 tons

Resource code

Cost element name

Unit measured

36-01-001-01

36-01-001-02

36-01-001-03

36-01-001-04

1

person-hour

15,85

14,15

31,08

27,49

1.1

Average job level

2

Driver labor costs

person-hour

19,33

14,92

36,63

19,99

3

MACHINES AND MECHANISMS

010311

mach.-h

1,21

0,67

010313

Crawler tractors for other types of construction 96 kW (130 hp)

mach.-h

13,62

010314

Crawler tractors for other types of construction 121 kW (165 hp)

mach.-h

1,43

1,79

010315

Crawler tractors when working on other types of construction 132 kW (180 hp)

mach.-h

0,81

1,15

070102

mach.-h

12,65

10,63

14,63

13,31

090102

mach.-h

1,21

0,67

120701

Trailed cam road rollers 8 t

mach.-h

13,62

120711

Trailed road rollers with pneumatic wheels 25 t

mach.-h

1,43

1,79

120712

Trailed road rollers with pneumatic wheels 50 t

mach.-h

0,81

1,15

120801

mach.-h

3,93

3,85

120802

mach.-h

1,24

1,83

120910

mach.-h

120911

mach.-h

0,81

1,24

4

MATERIALS

407-9085

Priming

m 3

1025

1025

1025

1025

411-0001

Water

m 3

Table GESN 36-01-002 Construction of the top of the screens and cores

Scope of work:

Meter: 1000 m 3 soil

36-01-002-01 Construction of the upper part of the screens and cores

Resource code

Cost element name

Unit measured

36-01-002-01

1

Labor costs of construction workers

person-hour

41,47

1.1

Average job level

2

Driver labor costs

person-hour

31,48

3

MACHINES AND MECHANISMS

010311

Crawler tractors for other types of construction 59 kW (80 hp)

mach.-h

0,84

050102

mach.-h

0,65

070102

Bulldozers for hydropower construction and stripping operations 79 kW (108 hp)

mach.-h

17,71

090102

Reclamation disc harrows (without tractor)

mach.-h

0,84

120801

Semi-trailer rollers on pneumatic wheels with a 15 t tractor

mach.-h

2,48

120802

Semi-trailer rollers on pneumatic wheels with a 25 t tractor

mach.-h

1,44

120910

Pneumatic rollers 16 t

mach.-h

2,87

120911

Pneumatic rollers 30 t

mach.-h

1,39

121500

mach.-h

331101

mach.-h

331103

Electric rammers

mach.-h

0,56

4

MATERIALS

407-9085

Priming

m 3

1010

411-0001

Water

m 3

Table GESN 36-01-003 Dejected device

Scope of work:

01. Leveling the soil in layers. 02. Soil compaction with moisture. 03. Loosening the compacted underlying layer of clay soil before laying the subsequent one. 04. Construction and maintenance of entrances, exits and driveways along the embankment. 05. Cleaning vehicle bodies when unloading clay soils.

Meter: 1000 m 3 soil

36-01-003-01Depression device

Resource code

Cost element name

Unit measured

36-01-003-01

1

Labor costs of construction workers

person-hour

62,04

1.1

Average job level

2

Driver labor costs

person-hour

29,04

3

MACHINES AND MECHANISMS

010311

Crawler tractors for other types of construction 59 kW (80 hp)

mach.-h

0,81

050102

Mobile compressors with internal combustion engine pressure up to 686 kPa (7 atm), capacity 5 m 3 /min

mach.-h

1,38

070102

Bulldozers for hydropower construction and stripping operations 79 kW (108 hp)

mach.-h

13,86

090102

Reclamation disc harrows (without tractor)

mach.-h

0,81

120801

Semi-price rollers on pneumatic wheels with a 15 t tractor

mach.-h

2,72

120802

Semi-trailer rollers on pneumatic wheels with a 25 t tractor

mach.-h

1,49

120910

Pneumatic rollers 16 t

mach.-h

3,25

120911

Pneumatic rollers 30 t

mach.-h

1,54

121500

Tampers based on the T-130.1.G tractor

mach.-h

3,99

331101

Pneumatic rammers when operating from a stationary compressor

mach.-h

5,52

331103

Electric rammers

mach.-h

4

MATERIALS

407-9085

Priming

m 3

1010

411-0001

Water

m 3

Table GESN 36-01-004 Construction of dams, dikes, embankments by dumping soil into water

Scope of work:

for standard 1:

01. Construction of embankments for ponds. 02. Moving soil unloaded from dump trucks downhill into the water. 03. Construction and maintenance of entrances, exits and driveways along the embankment. 04. Cleaning vehicle bodies when unloading clay soils.

for standards 2, 3:

01. Construction of embankments for ponds. 02. Soil compaction with moisture. 03. Moving soil unloaded from dump trucks downhill into the water. 04. Construction and maintenance of entrances, exits and driveways along the embankment. 05. Cleaning vehicle bodies when unloading clay soils.

Meter: 1000 m 3 soil

Construction of dams, dikes, embankments by dumping soil into water:

36-01-004-01 in natural ponds and reservoirs

36-01-004-02 in artificial ponds in layers up to 2 m

36-01-004-03 in artificial ponds in layers up to 4 m

Resource code

Cost element name

Unit measured

36-01-004-01

36-01-004-02

36-01-004-03

1

Labor costs of construction workers

person-hour

24,2

29,59

13,75

1.1

Average job level

2

Driver labor costs

person-hour

14,08

19,9

16,83

3

MACHINES AND MECHANISMS

010311

Crawler tractors for other types of construction 59 kW (80 hp)

mach.-h

0,17

0,04

060326

Single-bucket diesel excavators with pneumatic wheels when working on water construction projects 0.25 m 3

mach.-h

0,19

0,09

070102

Bulldozers for hydropower construction and stripping operations 79 kW (108 hp)

mach.-h

14,08

17,49

14,96

090102

Reclamation disc harrows (without tractor)

mach.-h

0,17

0,04

120910

Pneumatic rollers 16 t

mach.-h

2,05

1,74

4

MATERIALS

101-1887

Asbestos-cement pressure pipes VT6´ 150 type 1

407-9085

Priming

m 3

1010

1010

1010

411-0001

Water

m 3

Subsection 1.2 SINUSES

Table GESN 36-01-008 Filling the sinuses

Scope of work:

01. Leveling the soil in layers. 02. Soil compaction with moisture. 03. Loosening the compacted underlying layer of clay soil before laying the subsequent one. 04. Construction and maintenance of entrances, exits and driveways along the embankment. 05. Cleaning vehicle bodies when unloading clay soils.

Meter: 1000 m 3 soil

Sinus filling volume:

36-01-008-01 over 10000 m 3 with non-cohesive soils

36-01-008-02 over 10000 m 3 with cohesive soils

36-01-008-03 up to 10000 m 3 with non-cohesive soils

36-01-008-04 up to 10000 m 3 with cohesive soils

36-01-008-05 up to 200 m 3 with non-cohesive soils

36-01-008-06 up to 200 m 3 with cohesive soils

Resource code

Cost element name

Unit measured

36-01-008-01

36-01-008-02

36-01-008-03

1

Labor costs of construction workers

person-hour

44,75

63,51

73,7

1.1

Average job level

2

Driver labor costs

person-hour

21,07

27,61

27,98

3

MACHINES AND MECHANISMS

010311

Crawler tractors for other types of construction 59 kW (80 hp)

mach.-h

0,45

050102

Mobile compressors with internal combustion engine pressure up to 686 kPa (7 atm), capacity 5 m 3 /min

mach.-h

1,42

1,42

2,89

070102

Bulldozers for hydropower construction and stripping operations 79 kW (108 hp)

mach.-h

11,33

13,86

13,09

090102

Reclamation disc harrows (without tractor)

mach.-h

0,45

120801

Semi-trailer rollers on pneumatic wheels with a 15 t tractor

mach.-h

1,65

120802

Semi-trailer rollers on pneumatic wheels with a 25 t tractor

mach.-h

0,94

1,39

120910

Pneumatic rollers 16 t

mach.-h

1,38

2,79

3,68

120911

Pneumatic rollers 30 t

mach.-h

0,84

1,32

121500

Tampers based on the T-130.1.G tractor

mach.-h

3,51

3,98

8,32

331101

Pneumatic rammers when operating from a stationary compressor

mach.-h

5,68

5,68

11,56

331103

Electric rammers

mach.-h

1,91

1,91

3,72

4

MATERIALS

407-9085

Priming

m 3

1010

1010

1010

411-0001

Water

m 3

Resource code

Cost element name

Unit measured

36-01-008-04

36-01-008-05

36-01-008-06

1

Labor costs of construction workers

person-hour

97,24

1.1

Average job level

2

Driver labor costs

person-hour

36,57

46,07

52.22

3

MACHINES AND MECHANISMS

010311

Crawler tractors for other types of construction 59 kW (80 hp)

mach.-h

0,76

050102

Mobile compressors with internal combustion engine pressure up to 686 kPa (7 atm), capacity 5 m 7 min

mach.-h

2,87

28,87

31.62

070101

Bulldozers for hydropower construction and stripping operations 59 kW (80 hp)

mach.-h

17,2

20,6

070102

Bulldozers for hydropower construction and stripping operations 79 kW (108 hp)

mach.-h

15,84

090102

Reclamation disc harrows (without tractor)

mach.-h

0,76

120910

Pneumatic rollers 16 t

mach.-h

7,67

121500

Tampers based on the T-130.1 .G tractor

mach.-h

9,43

331101

Pneumatic rammers when operating from a stationary compressor

mach.-h

11,48

115,5

126.5

331103

Electric rammers

mach.-h

3,72

4

MATERIALS

407-9085

Priming

m 3

1010

1010

1010

411-0001

Water

m 3

Table GESN 36-01-009 Layout of slopes of embankments of earthen structures

Scope of work:

01. Layout of embankment slopes with cutting off irregularities and filling depressions.

Meter: 1000 m2 of planned surface

Layout of slopes of embankments of earthen structures:

36-01-009-01excavators

36-01-009-02 bulldozers

36-01-009-03auto graders

Resource code

Cost element name

Unit measured

36-01-009-01

36-01-009-02

36-01-009-03

Driver labor costs

person-hour

19,92

5,43

0,91

3

MACHINES AND MECHANISMS

060203

Single-bucket diesel excavators on caterpillar tracks when working on hydropower construction 0.65 m 3

mach.-h

5,96

060204

Single-bucket diesel excavators on caterpillar tracks when working on hydropower construction 1 m 3

mach.-h

3,94

060205

Single-bucket diesel excavators on caterpillar tracks when working on hydropower construction 1.25 m 3

mach.-h

3,04

070101

Bulldozers for hydropower construction and stripping operations 59 kW (80 hp)

mach.-h

1,85

070102

Bulldozers for hydropower construction and stripping operations 79 kW (108 hp)

mach.-h

1,58

070104

Bulldozers for hydropower construction and stripping operations 121 kW (165 hp)

mach.-h

1,09

070105

Bulldozers for hydropower construction and stripping operations 132 kW (180 hp)

mach.-h

0.91

120202

Medium motor graders 99 kW (135 hp)

mach.-h

Operation of the pond and dams includes activities for the supervision and maintenance of the dam and spillway structures, their repair and activities for the improvement of the pond area.

The main types of damage are water overflow over the dam crest; water filtration through a dam; destruction of a dam by a breakwater; damage to drainage structures.

Overflow of water over the ridge is observed during very large floods or due to the unpreparedness of spillway structures to handle the flood. To prevent water overflow, spillway structures must be cleared of snow, ice, and debris in the spring before the flood. In case of large floods, when the spillway structures do not have time to discharge water, in order to eliminate the overflow of water, it is necessary to build a temporary drainage canal with water drainage into the beam below the dam.

Cracks often form in new dams before the soil has completely settled due to freezing in the upper layers and continued settlement of the lower layers, leading to the formation of voids. If a transverse crack forms in the dam, you need to dig a trench 1.5-2.0 m deep 0.5 m below the depth of the crack. For a longitudinal crack, a trench is dug along the crack along its entire length. The crack is filled with the same soil from which the dam is made, in layers of 1 5-20 cm with careful compaction.

Filtration of water through a dam can occur if design or construction rules are violated. To eliminate filtration, it is necessary to increase the base of the dam by widening it on the side of the dry slope or to arrange drainage. If the water filtering through the drainage device is clean, this indicates that the dam is in good condition.

The destruction of the dam by a breakwater is eliminated by securing the wet slope with a stone blind area, concrete slabs, or throwing stones over squares made from willow stakes.

Spillways should be constantly cleared of debris, and in the spring of snow and ice. The most common types of damage to spillway structures is the formation of failures along their walls due to water filtration. Dips behind the walls of culverts should be promptly filled with soil.

In order to avoid the erosion of dams, it is necessary to organize observation and concentrate the necessary materials and mechanisms at the time of flood or flood.

The system of operational measures includes landscaping the area around the pond, restoring damaged turf, and creating tree and shrub plantings (the range of species is selected depending on soil and climatic conditions). On the banks of the reservoir along the water's edge, especially in places where the shore is destroyed by a breakwater, it is advisable to plant shrubby willows. When using a pond to extinguish fires, access roads and platforms are built at the water intake points

Periodically it is necessary to clean the pond from herbaceous aquatic vegetation. Small ponds are cleaned by hand; large ponds are cleaned using special mowers and dredgers. After 20-30 years, having completely freed the pond from water, it is cleaned of vegetation, debris and silt. Water is drained through a drain.

CHAPTER V

CALCULATION OF THE ECONOMIC COST OF THE PROJECT

5.1.Construction cost estimate

The cost estimate for the construction of a pond and dam is compiled item by item based on aggregated indicators, which are given in the table.

Table.6.

COST ESTIMATE

for the construction of a pond and dam according to aggregate indicators

Name of works

Mechanisms

Scope of work

Price, rub.

Cost, rub.

1 . Clearing areas of bushes and small forests

Uprooter-gatherer, brushcutter

2. Dam construction

installation of a castle trench and castle along the entire length of the dam

Scraper, bucket 2.25 m3

c) filling the dam

Scraper, bucket

d) soil compaction

Soil compaction machine-

3. Fastening the dam slopes:

Sod in a cage with adding vegetable soil and sowing herbs

4. Soil preparation, cost of seedlings, planting and forest care

Forestry machines

Total costs

Overhead costs - 16% 126067.98·0.16=20170rub

Planned savings - 6% 126067.98·0.06=7564.08 rub.

Unforeseen expenses - 3%. 126067.98·0.03=3782.04 rub.

TOTAL: 157584.1 rub.

5.2. Project passport

After completing the design work and economic calculations a project passport is also drawn up, which indicates the main parameters of the dam and pond at the time of creation and outlines the necessary operations for the operation of the dam and pond.

Ministry of Forestry of Russia

Forestry Department_

The cost estimate for the construction of a pond and dam is compiled item by item based on aggregated indicators, which are given in the table.

Table.6.

COST ESTIMATE

for the construction of a pond and dam according to aggregate indicators

Name of works

Mechanisms

Scope of work

Price, rub.

Cost, rub.

1 . Clearing areas of bushes and small forests

Uprooter-gatherer, brushcutter

2. Dam construction

a) removal of plant soil under the entire base of the dam to a depth of 0.4 m

Scraper, bucket 2.25 m 3

b) installation of a castle trench and castle along the entire length of the dam

Scraper, bucket 2.25 m 3

c) filling the dam

Scraper, bucket

d) soil compaction

Soil compaction machine-

e) planning of slopes and dam crest

Trailed graders

3. Fastening the dam slopes:

Sod in a cage with adding vegetable soil and sowing herbs

4. Soil preparation, cost of seedlings, planting and forest care

Forestry machines

Total costs

Overhead costs - 16% = 4389.8 rubles.

Planned savings - 6% = 1646.1 rub.

Unforeseen expenses - 3% = 823 rub.

TOTAL: RUB 34,295.3

5.2. Project passport

After completing the design work and economic calculations, a project passport is drawn up, which indicates the main parameters of the dam and pond at the time of creation and outlines the necessary operations for the operation of the dam and pond.

Ministry of Forestry of Russia

Forestry Department______________________________

Forestry (lespromkhoz)_______________________________

Locality__________________________________

dams and ponds built according to project No._ 9

    Region) Republic of Tatarstan

    Area_________________________________________________________

3. Nature of the catchment area ________________________________________________________________

4. Time of design and survey work_________________________________________________________________

5. Construction time __________________________

6. Main characteristics of the dam:

the dam foundation soil is permeable_________

dam soil medium loam __________________

anti-filtration structures;

There is no dam in the body, there is a lock under the dam, the length of the dam is _____________

dam height_______ ________________________________________

ridge width ________________________________________________

spillway structure _____________________________________________

7. Main characteristics of the pond: water surface area at the gas station ___________________

___________________

water depth at the dam _______________

length along the axis of the pond ______________________________

width of the pond at the dam (according to NPG) _________

greatest ____________

8. Characteristics of the protective forest belt: strip length 2750

The width of the line 50 , rows 3 things

tree species Pine, poplar

shrub species _______________________

9. Pond cleaning measures ______________

spillway cleaning _________________________

Regular care of plantings_____________

seasonal cleaning of recreation areas__________________